Building Material City

Project Information

Installation & Termination of Low Voltage systems - Fire Alarm systems, Building Management System, Access control system & CCTV systems

In Shopping mall

  • Fire Alarm: Cable installation of over 27 Kms FP200 Cable, device fixing and termination of smoke detectors (700), break glass (50) and control relay modules
  • BMS: Cable  installation over 263 Kms of 1.5mm  Signal wire, device termination of dampers, FCU controllers, etc.)
  • Access control: Cable installation of over 17 Kms of Belden cables, device fixing and termination of card readers, door contacts, access intelligent controllers
  • CCTV: Cable installation of over 120 Kms of RG6 Cable, device fixing and termination of indoor dome cameras

In Tower 16 & 17

  • Fixing, termination and testing of addressable modules in Emergency light (over 1200 + lights)
  • CCTV Rack termination and testing of 51 Cameras in Tower 16
  • Client : Toledo
  • Date : January 2010 – December 2010
  • Location : Abu Dhabi
  • Project Name : Building Material City
  • Employees : 30